HONG KONG LEGISLATIVE COUNCIL.
SCHEDULE.
Appendix VI (C).
LOAN WORKS.
Additional Works to be charged to a proposed New Loan.
65
Works.
Revised Estimated cost.
Expenditure Expenditure
for 1938.
for 1939.
$
$
$
Head 1.-New Markets:
(a) Central Market
50,000.00
50,000.00
Head 1.-Total
* 50,000.00
50,000.00
Head 2.-Water Works:-
Authorized Works. (a) Supply to Albany (b) Supply to Peak Road (c) Cross Harbour Pipes (d) Rapid Gravity Filters,
Eastern
100,000.00
79,019.99
19,458.82
130,000.00
51,676.34
76,818.60
900,000.00
576,942.05
268,198.88
490,000.00
9,442.72
50,000.00
(e) Kowloon Chai Service
Reservoir
240,000.00
19,726.87 180,000.00
(f) Supply Main to Kow-
loon Chai Service Re- servoir
250.000.00
(g) Distribution, Island (h) Distribution, Mainland (i) Shing Mun Valley
Scheme Catchwaters Proposed New Works:-
(j) Rapid Gravity Filters, Shing Mun Valley Scheme
100,000.00
17,878.64
200,000.00 35,000.00 75,000.00 40,366.34 25,000.00
1,854.95
1,070,000.00
213,641.86
360,000.00
150,000.00
120,000.00
(k) Tai
Lam Chung
Scheme, Preliminary
Works
(1) New Meters
70,000.00 10,000.00
50,000.00
170,000.00
110,000.00
(m) Waste Detection
Equipment
300,000.00
120,000.00
(n) Reconstruction at Al-
bany
150,000.00
(0) Miscellaneous
Works
67,500.00
67,500.00
Head 2.-Total
4,262,500.00 1,020.549.76 1,681,976.30
Grand Total
4,312,500.00 1,020.549.76 1,731.976.30
* Part Cost: Total cost is $910,126.10 of which $860,126.10 is chargeable